The ProgrammeThe Airport's Operational Improvements Programme, unveiled late in 2000, has three elements: West End ImprovementsThese improvements, completed in August 2002, included:
The re-routing of the original footpath linking Hartmann Road with the Piazza under the Connaught Crossing required an order under sections 247 and 253 of the Town and Country Planning Act 1990 to stop-up the original footpath and for the construction of the replacement path round the new boundary of the Airport. |
|||||||||||
![]() |
|||||||||||
|
|||||||||||
![]() |
![]() |
![]() |
|
East Apron Extension - work in progress January 2008 |
|||
In May 2007 the Airport announced it had placed a contract worth £19m with support services and construction company Carillion for this extension project. The contract is for the construction of a 20,000 square metre concrete platform, supported by piles and built over the King George V Dock to the east of the existing terminal. In addition, a sound screen will be incorporated to minimise noise impact of aircraft operations on neighbouring houses. Construction started in June 2007 and the new stands will be in service during the summer of 2008. As with the construction of the Hold Point in 2003, the main site compound is located at the old Mowlem Training Building and most of the activity is being undertaken from the dock.
The major construction work is also similar the previous scheme, and is being carried out at weekends and overnight. Contact numbers are available within the local community in case of need to contact the site in relation to the works.
The project involves 217 concrete piles to support the new apron. Each of these is 1m in diameter and they act as a matrix to transfer the massive load of the structure, plus the aircraft to be parked on top of it, 20m to the bottom of the dock. The new apron is a matrix of 10-25 tonne concrete beams and planks - 1600 of them. They are being cast west of the Connaught Bridge and then shipped to the new apron.
Rainfall on the airfield is transferred to the sewers by a system of chambers and pipes. To connect the new apron to the existing airfield system means the installation of 0.5 km of new pipes and 10 new chambers.
Top of PagePlanning permission for the apron and holding point improvements was finally granted in September 2001subject to an agreement under s.106 of the Town and Country Planning Act 1990 which it is understood will focus principally on the funding of the Airport Extension of the Dockland Light Railway. The discussions on the application included consideration of the noise arising from the construction of the new facilities and measures were agreed aimed at minimising this.
A copy of the planning report considered by the London Borough of Newham's Planning and Licensing Committee is attached (Acrobat .pdf format - 55K).
See the slide presentation shown to the Consultative Committee in April 2000.
An independent Consultative Committee established by London City Airport pursuant to Section 35 of the Civil Aviation Act 1982
Chairman: John Adshead Secretary: Stuart Innes
E-Mail
Page last modified: 1st August 2008